convert 13 weeks of data to calendar months
convert 13 weeks of data to calendar months
I have a 13 column browse. Each column represents a week. The weeks are consecutive.
The Browse looks like this:
Headers: 7/15/10-07/22/10-07/29/10-08/05/10-8/12/10-08/19/10-08/26/10-09/02/10-09/09/10-09/16/10-09/23/10-09/30/10
As you can see the 13 week columns span three calendar months. July, August and September. Each of the columns contains a value for the week indicated.
My need is to convert the 13 week information to calendar dates by the number of days in a month. As you know there are 13 week’s in the calendar quarter. July has 31 days, August has 31 days in September has 30 days.
Has anyone put together some code converting the 13 weeks of data into three calendar months. The biggest problem comes about when a week spans two months. Thus some of the values in that week need to go to the month before and some need to go to the month after.
For example the August 5-week needs to be split between July and August by days. And the September 2 week needs to be split between August and September by days.
The per day value is developed by taking the weeks value and dividing by 7.
All help will be appreciated.
The Browse looks like this:
Headers: 7/15/10-07/22/10-07/29/10-08/05/10-8/12/10-08/19/10-08/26/10-09/02/10-09/09/10-09/16/10-09/23/10-09/30/10
As you can see the 13 week columns span three calendar months. July, August and September. Each of the columns contains a value for the week indicated.
My need is to convert the 13 week information to calendar dates by the number of days in a month. As you know there are 13 week’s in the calendar quarter. July has 31 days, August has 31 days in September has 30 days.
Has anyone put together some code converting the 13 weeks of data into three calendar months. The biggest problem comes about when a week spans two months. Thus some of the values in that week need to go to the month before and some need to go to the month after.
For example the August 5-week needs to be split between July and August by days. And the September 2 week needs to be split between August and September by days.
The per day value is developed by taking the weeks value and dividing by 7.
All help will be appreciated.
Thank you
Harvey
Harvey
- James Bott
- Posts: 4840
- Joined: Fri Nov 18, 2005 4:52 pm
- Location: San Diego, California, USA
- Contact:
Re: convert 13 weeks of data to calendar months
Harvey,
I read you message a couple of times and I am still not clear on what you are trying to do. Are you saying that you already have data for each week, and now you want to convert it to data for each month?
If so, I would find the data for each day by dividing the week data by 7, then summarize the data by adding all the daily data for each month.
Create a two-dimesional array with two elements; one for the date, and one for the total. Then fill the array with dates and totals, then summarize for each month.
James
I read you message a couple of times and I am still not clear on what you are trying to do. Are you saying that you already have data for each week, and now you want to convert it to data for each month?
If so, I would find the data for each day by dividing the week data by 7, then summarize the data by adding all the daily data for each month.
Create a two-dimesional array with two elements; one for the date, and one for the total. Then fill the array with dates and totals, then summarize for each month.
James
Re: convert 13 weeks of data to calendar months
Thanks for the response.
Problem is when a week covers 2 months. Need to have an easy method to slpit the week up between the months
The main issue is to know how many days in the month so you only account for the days in the month, no more no less. say july 31days ...week one 3 days in June and 4 days in july, week two has 7 days in july, week 3 has 7 days july, week 4 has 7 days july, week 5 has 6 days in july and one day in August.
July week1 = 4 days
week2 = 7 days
week3 = 7 days
week4 = 7 days
week5 = 6 days
total days 31
Just looking for an easy way to accomplish this without many lines of code.
I can do it but take lot of time. Maybe with you skills you have a suggestion. If you call I'm not a programer. Just an accountant with one program.
Thanks for any suggestions.
Problem is when a week covers 2 months. Need to have an easy method to slpit the week up between the months
The main issue is to know how many days in the month so you only account for the days in the month, no more no less. say july 31days ...week one 3 days in June and 4 days in july, week two has 7 days in july, week 3 has 7 days july, week 4 has 7 days july, week 5 has 6 days in july and one day in August.
July week1 = 4 days
week2 = 7 days
week3 = 7 days
week4 = 7 days
week5 = 6 days
total days 31
Just looking for an easy way to accomplish this without many lines of code.
I can do it but take lot of time. Maybe with you skills you have a suggestion. If you call I'm not a programer. Just an accountant with one program.
Thanks for any suggestions.
Thank you
Harvey
Harvey
Re: convert 13 weeks of data to calendar months
Hello Harvey,
maybe that could work for You ???
Your Question :
Problem is when a week covers 2 months.
Need to have an easy method to slpit the week up between the months
The Calculation is included in my Date / Time Funktion-Collection


Of any given date :
1. calculates the weeknumber
2, 3. calculates the start- and enddate of the weeknumer.
it shows, if the calculated week of a given date is included in one Month or two.
Best Regards
Uwe
maybe that could work for You ???
Your Question :
Problem is when a week covers 2 months.
Need to have an easy method to slpit the week up between the months
The Calculation is included in my Date / Time Funktion-Collection


Of any given date :
1. calculates the weeknumber
2, 3. calculates the start- and enddate of the weeknumer.
it shows, if the calculated week of a given date is included in one Month or two.
Best Regards
Uwe

Since 1995 ( the first release of FW 1.9 )
i work with FW.
If you have any questions about special functions, maybe i can help.
i work with FW.
If you have any questions about special functions, maybe i can help.
- James Bott
- Posts: 4840
- Joined: Fri Nov 18, 2005 4:52 pm
- Location: San Diego, California, USA
- Contact:
Re: convert 13 weeks of data to calendar months
You guys are over complicating it.
By calculating the total for each day you can easily figure out how much for each month--you don't need to know when a week is split between two months. Forget weeks after converting the data to days.
You can use the Month( dDate ) function to find all days in a month--you don't need to figure out how many days in each month; the month() function will take care of it.
You fill an array with the data (date and amount) then start processing the array until you come to a new month, then start over with a new total.
James
By calculating the total for each day you can easily figure out how much for each month--you don't need to know when a week is split between two months. Forget weeks after converting the data to days.
You can use the Month( dDate ) function to find all days in a month--you don't need to figure out how many days in each month; the month() function will take care of it.
You fill an array with the data (date and amount) then start processing the array until you come to a new month, then start over with a new total.
James
Re: convert 13 weeks of data to calendar months
Uwe:
it is a bit complex. I want the user to enter on one button and it converts 13 weeks to 3 calendar months.
James:
Each of the 13 weeks has a different value. So the allocation of days within a week to the month must be made.
This has to be done the first week and last week of the month.
so far what I'm doing is taking 5 weeks to determine the months value.
week1 can be between split between 2 months
week2, week3, week4 always seven days and always same month
week5 makes up the difference in days between the total days used in week 1 to 4 compared to number of days in the month.
it is a bit complex. I want the user to enter on one button and it converts 13 weeks to 3 calendar months.
James:
Each of the 13 weeks has a different value. So the allocation of days within a week to the month must be made.
This has to be done the first week and last week of the month.
so far what I'm doing is taking 5 weeks to determine the months value.
week1 can be between split between 2 months
week2, week3, week4 always seven days and always same month
week5 makes up the difference in days between the total days used in week 1 to 4 compared to number of days in the month.
Thank you
Harvey
Harvey
- James Bott
- Posts: 4840
- Joined: Fri Nov 18, 2005 4:52 pm
- Location: San Diego, California, USA
- Contact:
Re: convert 13 weeks of data to calendar months
Harvey,
Understood. But as I said, the month() function will handle this for you.
Here is a sample done with the month() function. First the data is converted to daily data, then the daily data is summed by month. Simple.
Start with weekly data:
Week Starting Amount
1 07/15/10 100
2 07/22/10 122
3 07/29/10 127
4 08/05/10 117
Convert to daily data:
Date Amount
07/15/10 14.29 (100/7)
07/16/10 14.29
07/17/10 14.29
07/18/10 14.29
07/19/10 14.29
07/20/10 14.29
07/21/10 14.29
07/22/10 17.43 (122/7)
07/23/10 17.43
07/24/10 17.43
07/25/10 17.43
07/26/10 17.43
07/27/10 17.43
07/28/10 17.43
07/29/10 18.14 (127/7)
07/30/10 18.14
07/31/10 18.14
Find monthly data:
Month total 276.43
Isn't this what you are looking for?
James
Each of the 13 weeks has a different value. So the allocation of days within a week to the month must be made. This has to be done the first week and last week of the month.
Understood. But as I said, the month() function will handle this for you.
Here is a sample done with the month() function. First the data is converted to daily data, then the daily data is summed by month. Simple.
Start with weekly data:
Week Starting Amount
1 07/15/10 100
2 07/22/10 122
3 07/29/10 127
4 08/05/10 117
Convert to daily data:
Date Amount
07/15/10 14.29 (100/7)
07/16/10 14.29
07/17/10 14.29
07/18/10 14.29
07/19/10 14.29
07/20/10 14.29
07/21/10 14.29
07/22/10 17.43 (122/7)
07/23/10 17.43
07/24/10 17.43
07/25/10 17.43
07/26/10 17.43
07/27/10 17.43
07/28/10 17.43
07/29/10 18.14 (127/7)
07/30/10 18.14
07/31/10 18.14
Find monthly data:
Month total 276.43
Isn't this what you are looking for?
James
- nageswaragunupudi
- Posts: 10721
- Joined: Sun Nov 19, 2006 5:22 am
- Location: India
- Been thanked: 8 times
- Contact:
Re: convert 13 weeks of data to calendar months
Further simplifying the above logic calculate aggregate for the quarter and adjust for first and last weeks.
When the first or last week extends to previous or next quarter, reduce proportionately by that week's daily average.
It also happens that first week starts later than the 1st day of calendar quarter or last day ends earlier than the last of day of calendar quarter. In such cases we need values for last week of previous 52wk quarter or 1st week of next quarter to get accurate result. If we don't have those values, we need to extrapolate this quarter's tail week values.
For more accurate conversions we also need to know if the transactions are 5days or 6days or 7days a week.
A generic function can be attempted which requires the following paramters:
1. Aggregate of 13week quater.
2. First date of the quarter
3. First week value
4. Last week value
Optionally
5. Last week value of previous quarter
6. First week value of next quarter
Here is a quick attempt ( untested )
When the first or last week extends to previous or next quarter, reduce proportionately by that week's daily average.
It also happens that first week starts later than the 1st day of calendar quarter or last day ends earlier than the last of day of calendar quarter. In such cases we need values for last week of previous 52wk quarter or 1st week of next quarter to get accurate result. If we don't have those values, we need to extrapolate this quarter's tail week values.
For more accurate conversions we also need to know if the transactions are 5days or 6days or 7days a week.
A generic function can be attempted which requires the following paramters:
1. Aggregate of 13week quater.
2. First date of the quarter
3. First week value
4. Last week value
Optionally
5. Last week value of previous quarter
6. First week value of next quarter
Here is a quick attempt ( untested )
Code: Select all | Expand
function Q13ToCalQuarter( nTotal, dFirstDay, nFirstWeek, nLastWeek, nPrevWeek, nNextWeek )
local n
n := DAY( dFirstDay ) - 1
if n > 0
if n < 7
nTotal += ( n * If( nPrevWeek == nil, nFirstWeek, nPrevWeek ) / 7 )
else
n := EOM( dFirstDay ) - dFirstDay + 1
nTotal -= ( n * nFirstWeek / 7 )
endif
endif
dFirstDay += 91 // first day of next quarter
n := DAY( dFirstDay ) - 1
if n > 0
? n
if n < 7
nTotal -= ( n * nLastWeek / 7 )
else
n := EOM( dFirstDay ) - dFirstDay + 1
nTotal += ( n * If( nNextWeek == nil, nLastWeek, nNextWeek ) / 7 )
endif
endif
return nTotal
Regards
G. N. Rao.
Hyderabad, India
G. N. Rao.
Hyderabad, India
- James Bott
- Posts: 4840
- Joined: Fri Nov 18, 2005 4:52 pm
- Location: San Diego, California, USA
- Contact:
Re: convert 13 weeks of data to calendar months
Rao,
You bring up a significant point--what are the rules?
I note that in Harvey's original message he shows only 12 weeks, yet he specifies 13 weeks. And the sample data he shows starts on 7/15/10. Thirteen weeks from 7/15/10 ends on 10/13/10.
I would assume that monthly data for three months should be the range from 7/1/10 to 9/30/10. If that is the range needed, then it is not possible to convert the 13 weeks of data specified to monthly data. You would actually need data from the previous couple of weeks.
It would be ideal to have the daily data for each day of the year (YTD) and from that you can find weekly and monthly data with accuracy.
It has been some time since I studied accounting so I don't know what the conventional methods are.
Regards,
James
You bring up a significant point--what are the rules?
I note that in Harvey's original message he shows only 12 weeks, yet he specifies 13 weeks. And the sample data he shows starts on 7/15/10. Thirteen weeks from 7/15/10 ends on 10/13/10.
I would assume that monthly data for three months should be the range from 7/1/10 to 9/30/10. If that is the range needed, then it is not possible to convert the 13 weeks of data specified to monthly data. You would actually need data from the previous couple of weeks.
It would be ideal to have the daily data for each day of the year (YTD) and from that you can find weekly and monthly data with accuracy.
It has been some time since I studied accounting so I don't know what the conventional methods are.
Regards,
James
Re: convert 13 weeks of data to calendar months
so far I have a solution except the 13 week period must start at the beginning of a month or within 7 days before the beginning of the month.
heres my code:
I've tested if for 13 weeks beginning 6/01/0...7/07/10...5/01/10
It works.
heres my code:
Code: Select all | Expand
function airrpt()
local cDate99 //:= date()-17
local cDate1
local cDate2
local cDate3
local cDate4
local cDate5
local cDate6
local cDate7
local cDate8
local cDate9
local cDate10
local cDate11
local cDate12
local cDate13, nVar := 0
local nTotal1 :=0
local nTotal2 :=0
local nTotal3 :=0
// weekly values
local nCf1 := 700
local nCf2 := 1400
local nCf3 := 2100
local nCf4 := 2800
local nCf5 := 3500
local nCf6 := 4200
local nCf7 := 4900
local nCf8 := 5600
local nCf9 := 6300
local nCf10 := 7000
local nCf11 := 7700
local nCf12 := 8400
local nCf13 := 9100
local nCf1a := 0
local nCf5a := 0
local nNum1 := 0
local nNum2 := 0
local nNum3 := 0
local nNum4 := 0
local nNum5 := 0
local nNum6 := 0
local nNum7 := 0
local nNum8 := 0
local nNum9 := 0
local nNum10 := 0
local nNum11 := 0
local nNum12 := 0
local nNum13 := 0
local nDate1, nDays := 0
local nDate2
local nDate3
local nDate4
local nDate5
local nDate6
local nDate7
local nDate8
local nDate9
local nDate10
local nDate11
local nDate12
local nDate13
use "20100701.d10" alias Mthly
index on mthly->account to nMthly
cDate99 := ctod("07/01/10")
cDate1 := cDate99+6
cDate2 := cDate99+(7*2) -1
cDate3 := cDate99+(7*3) -1
cDate4 := cDate99+(7*4) -1
cDate5 := cDate99+(7*5) -1
cDate6 := cDate99+(7*6) -1
cDate7 := cDate99+(7*7) -1
cDate8 := cDate99+(7*8) -1
cDate9 := cDate99+(7*9) -1
cDate10 := cDate99+(7*10)-1
cDate11 := cDate99+(7*11)-1
cDate12 := cDate99+(7*12)-1
cDate13 := cDate99+(7*13)-1
cDate1 := dtoc(cDate1)
cDate2 := dtoc(cDate2)
cDate3 := dtoc(cDate3)
cDate4 := dtoc(cDate4)
cDate5 := dtoc(cDate5)
cDate6 := dtoc(cDate6)
cDate7 := dtoc(cDate7)
cDate8 := dtoc(cDate8)
cDate9 := dtoc(cDate9)
cDate10 := dtoc(cDate10)
cDate11 := dtoc(cDate11)
cDate12 := dtoc(cDate12)
cDate13 := dtoc(cDate13)
mthly->(dbgotop())
do while mthly->account < "9850"
// getting weekly values from 13 week report
nCf1 := mthly->cf1
nCf2 := mthly->cf2
nCf3 := mthly->cf3
nCf4 := mthly->cf4
nCf5 := mthly->cf5
nCf6 := mthly->cf6
nCf7 := mthly->cf7
nCf8 := mthly->cf8
nCf9 := mthly->cf9
nCf10 := mthly->cf10
nCf11 := mthly->cf11
nCf12 := mthly->cf12
nCf13 := mthly->cf13
if nCf1 +;
nCf2 +;
nCf3 +;
nCf4 +;
nCf5 +;
nCf6 +;
nCf7 +;
nCf8 +;
nCf9 +;
nCf10+;
nCf11+;
nCf12+;
nCf13 <= 0
mthly->(dbskip())
loop
endif
//Month 1
nNum1 := 7-(val(SUBSTR(cDate1,4,2)))
nNum2 := 0 // always 7 days
nNum3 := 0 // always 7 days
nNum4 := 0 // always 7 days
nNum5 := 7-(val(SUBSTR(cDate5,4,2)))
// ADD TO THE BEGINNING OF THE MONTH
nCf1a := nCf1/7 // 1st week daily average
nCf5a := nCf5/7 // last week "
if nNum1 == 0
nNum1 := nCf1
else
nNum1 := 7-nNum1
nNum1 := nNum1*nCf1a
endif
if nNum2 == 0
nNum2 := nCf2
endif
if nNum3 == 0
nNum3 := nCf3
endif
if nNum4 == 0
nNum4 := nCf4
endif
if nNum5 == 0
nNum5 := nCf5
else
nNum5 := nNum5*nCf5a
endif
nTotal1 := nNum1+;
nNum2+;
nNum3+;
nNum4+;
nNum5
//Month 2
nNum5 := 7-nNum5/nCf5a
nNum6 := 0
nNum7 := 0
nNum8 := 0
nNum9 := 7-(val(SUBSTR(cDate9,4,2)))
nCf1a := nCf5/7 // 1st week
nCf5a := nCf9/7 // last week
if nNum5 == 0
nNum5 := nCf5
else
nNum5 := nNum5*nCf1a
endif
if nNum6 == 0
nNum6 := nCf6
endif
if nNum7 == 0
nNum7 := nCf7
endif
if nNum8 == 0
nNum8 := nCf8
endif
if nNum9 == 0
nNum9 := nCf9
else
nNum9 := nNum9*nCf5a
endif
nTotal2 := nNum5+;
nNum6+;
nNum7+;
nNum8+;
nNum9
//Month 3
nNum9 := 7-nNum9/nCf5a
nNum10 := 0
nNum11 := 0
nNum12 := 0
nNum13 := 7-(val(SUBSTR(cDate13,4,2)))
if nNum13 < 0
nNum13 := 0
endif
nCf1a := nCf9/7 // 1st week
nCf5a := nCf13/7 // last week
if nNum9 == 0
nNum9 := nCf9
else
nNum9 := nNum9*nCf1a
endif
if nNum10 == 0
nNum10 := nCf10
endif
if nNum11 == 0
nNum11 := nCf11
endif
if nNum12 == 0
nNum12 := nCf12
endif
if nNum13 == 0
nNum13 := nCf13
else
nNum13 := nNum13*nCf5a
endif
nTotal3 := nNum9+;
nNum10+;
nNum11+;
nNum12+;
nNum13
// which quarter here
mthly->mth7 := nToTal1
mthly->mth8 := nToTal2
mthly->mth9 := nToTal3
mthly->mth13 := mthly->mth1 +;
mthly->mth2 +;
mthly->mth3 +;
mthly->mth4 +;
mthly->mth5 +;
mthly->mth6 +;
mthly->mth7 +;
mthly->mth8 +;
mthly->mth9 +;
mthly->mth10 +;
mthly->mth11 +;
mthly->mth12
* ? nToTal1 +;
* nToTal2 +;
* nToTal3
nNum1 := 0
nNum2 := 0
nNum3 := 0
nNum4 := 0
nNum5 := 0
nNum6 := 0
nNum7 := 0
nNum8 := 0
nNum9 := 0
nNum10 := 0
nNum11 := 0
nNum12 := 0
nNum13 := 0
mthly->(dbskip())
loop
enddo
set filter to !mthly->mth13 == 0
//browse()
//newBrowse()
return nil
I've tested if for 13 weeks beginning 6/01/0...7/07/10...5/01/10
It works.
Thank you
Harvey
Harvey
- James Bott
- Posts: 4840
- Joined: Fri Nov 18, 2005 4:52 pm
- Location: San Diego, California, USA
- Contact:
Re: convert 13 weeks of data to calendar months
Harvey,
I think you would benefit by learning to use arrays. This can signigicantly reduce your coding time.
Example. This code can be reduced:
Using an array, all of the above code can be written as below. It is also not good practice to assign data of the wrong type to variables with Hungarian notation (e.g. assigning date types to variables begining with "c" then changing the type). The problem with doing this is that you never know what type of data the varible holds. Here I have not done that. We have reduced 26 lines of code to 4 lines of code. This is a 80% reduction. You also reduce the possibility of typos which can lead to really hard to find errors.
I don't think that 13 weeks is enough. Couldn't it be 14 or 15 weeks if the start date falls on a Sunday and/or the end date falls on a Saturday?
It still seems easier to me to use daily data. Do you have raw daily data?
Regards,
James
I think you would benefit by learning to use arrays. This can signigicantly reduce your coding time.
Example. This code can be reduced:
Code: Select all | Expand
cDate99 := ctod("07/01/10")
cDate1 := cDate99+6
cDate2 := cDate99+(7*2) -1
cDate3 := cDate99+(7*3) -1
cDate4 := cDate99+(7*4) -1
cDate5 := cDate99+(7*5) -1
cDate6 := cDate99+(7*6) -1
cDate7 := cDate99+(7*7) -1
cDate8 := cDate99+(7*8) -1
cDate9 := cDate99+(7*9) -1
cDate10 := cDate99+(7*10)-1
cDate11 := cDate99+(7*11)-1
cDate12 := cDate99+(7*12)-1
cDate13 := cDate99+(7*13)-1
cDate1 := dtoc(cDate1)
cDate2 := dtoc(cDate2)
cDate3 := dtoc(cDate3)
cDate4 := dtoc(cDate4)
cDate5 := dtoc(cDate5)
cDate6 := dtoc(cDate6)
cDate7 := dtoc(cDate7)
cDate8 := dtoc(cDate8)
cDate9 := dtoc(cDate9)
cDate10 := dtoc(cDate10)
cDate11 := dtoc(cDate11)
cDate12 := dtoc(cDate12)
cDate13 := dtoc(cDate13)
Using an array, all of the above code can be written as below. It is also not good practice to assign data of the wrong type to variables with Hungarian notation (e.g. assigning date types to variables begining with "c" then changing the type). The problem with doing this is that you never know what type of data the varible holds. Here I have not done that. We have reduced 26 lines of code to 4 lines of code. This is a 80% reduction. You also reduce the possibility of typos which can lead to really hard to find errors.
Code: Select all | Expand
dDate99 := ctod("07/01/10")
for i = 1 to 13
cDate[i] := dtoc( dDate99 + 7*i) -1 )
next
I don't think that 13 weeks is enough. Couldn't it be 14 or 15 weeks if the start date falls on a Sunday and/or the end date falls on a Saturday?
It still seems easier to me to use daily data. Do you have raw daily data?
Regards,
James
Re: convert 13 weeks of data to calendar months
James:
No daily data avaialable and 13 weeks is a calendar quarter. So changing to 14 or 15 weeks is not an option.
THanks all fo the help.
No daily data avaialable and 13 weeks is a calendar quarter. So changing to 14 or 15 weeks is not an option.
THanks all fo the help.
Thank you
Harvey
Harvey
- James Bott
- Posts: 4840
- Joined: Fri Nov 18, 2005 4:52 pm
- Location: San Diego, California, USA
- Contact:
Re: convert 13 weeks of data to calendar months
Harvey,
So you cannot generate certain monthly data without making guesses. For example, if your quarterly data starts on 7/15 then you have no data from 7/1 through 7/14. So, the only possibility is to generate sales for that period using existing data. This may be very inaccurate especially when data is affected by seasons.
My fear is that when you calculate data using guesses, and don't make a very strong point of it when displayed to the users, they will take it as real. I find that this information must be displayed every time the data is displayed or users will forget or new users will not know.
If users are using data that is unrelable to make business decisions, it could have catastrophic effects.
Regards,
James
No daily data avaialable and 13 weeks is a calendar quarter. So changing to 14 or 15 weeks is not an option.
So you cannot generate certain monthly data without making guesses. For example, if your quarterly data starts on 7/15 then you have no data from 7/1 through 7/14. So, the only possibility is to generate sales for that period using existing data. This may be very inaccurate especially when data is affected by seasons.
My fear is that when you calculate data using guesses, and don't make a very strong point of it when displayed to the users, they will take it as real. I find that this information must be displayed every time the data is displayed or users will forget or new users will not know.
If users are using data that is unrelable to make business decisions, it could have catastrophic effects.
Regards,
James